PROJECT DESCRIPTION

Construction of a sewer pump station.

  • SJC revised the design of the pump station to facilitate caisson construction techniques, reducing the cost of the project by over $500,000.00 at bid time.
  • Largest caisson type construction of a pump station west of the Mississippi (50’x45’x47’ deep).
  • 4.5 MGD pump station
  • Included a 6300 sf pre-engineered maintenance building.
  • Excavation to 37’ below the water table.