WWTF Improvements

BID CLOSE DATE

2021.02.18

BID CLOSE TIME

11:00 am

PROJECT LOCATION

Morton, WA

LEAD ESTIMATOR

Brint DeVilling

PHONE

360-225-7996

EMAIL
bids@stellarj.com
PROJECT DESCRIPTION

Schedule A: Wastewater Treatment Facility
Work includes the construction of a new headworks, secondary clarifiers, UV disinfection system, outfall, and Solids Handling Building. The work shall include modifications and/or demolition of the existing headworks, oxidation ditch, secondary clarifiers, chlorine contact tank, Operations Building, and sludge drying beds.
Schedule B: Oxidation Ditch Cleaning Project
Work includes furnishing all labor, materials, and equipment necessary for temporarily removing the oxidation ditch from service including the disposal of biosolids, cleaning, and structural repairs of oxidation ditch tank. While the oxidation ditch is out of service, the project includes furnishing and installing a temporary wastewater treatment system to include a temporary pump station, equalization tank, biological treatment system, piping, electrical and SCADA system.

Available Project Information

Preliminary Bid Results

  1. Pacific Crest

    10,167,598.99

  2. Rotschy

    10,843,674.81

  3. McClure and Sons

    11,181,731.79

  4. Stellar J

    11,524,666.23

  5. Pease & Sons

    12,046,336.30

Number of Bids Received

5